GUIDE / IMPORTED-TO-ORDER TIMING

How imported plasterboard lead time works.

There is no honest single lead-time number before the product, quantity, import-lot route, vessel timing, clearance and Auckland handover are confirmed. Panelform sets an estimated schedule in the written quote.

SIX STAGES

The schedule follows the confirmed supply route.

Product and quantity check

Confirm the exact board, customer quantity, supplier availability, evidence status and import-lot route.

Written landed quote

Set the included costs, exclusions, deposit, balance stages and estimated schedule before the customer commits.

Order acceptance

Procurement waits until the quote is accepted, Panelform confirms the order and the required deposit clears.

Supplier order and freight

Place the agreed order, prepare the shipment and coordinate the available sea-freight route.

Border and port handling

Complete the applicable import entry, clearance, port release and any inspection or storage steps.

Auckland delivery

Confirm the local vehicle, access, unloading, handover and customer inspection arrangements.

WHAT CHANGES TIMING

These inputs move the estimate.

  • Exact SKU, dimensions, quantity and supplier preparation
  • Whether the quantity uses a consolidated or other confirmed import-lot route
  • Vessel availability, sailing schedule and port conditions
  • Customs, MPI, inspection, storage or documentation requirements
  • Auckland delivery access, unloading and the required site window
Estimated dates are not guaranteed dates

The written quote identifies the current assumptions and estimated windows. Panelform provides reasonable updates when the route changes. Project teams should confirm local delivery before locking in labour or installation sequencing.

NEXT STEP

Send the quantity, location and required date.

We will identify the supply stages that can be confirmed and the timing questions still open before an order is accepted.